0%
Loading ...

Emergency Department & 1708 Lacey Building Renovations

Location

Cape Girardeau, MO

Owner

SoutheastHEALTH

Engineering Partner

Christner Architects

Services Provided

General Contractor

Contract Amount

$12.8M

Project Summary

Robinson was awarded a contract to perform as the general contractor on a renovation project for SoutheastHEALTH in Cape Girardeau, Missouri.

EMERGENCY DEPARTMENT (ED) RENOVATIONS

The ED Renovation was a multi-phase remodel of the existing Emergency Department at the SoutheastHEALTH hospital. The aging facility received upgraded systems, finishes, and a new layout to allow for more exam rooms. The ED remained functional throughout the entire project, which required close coordination with facility management, ED staff, and the design team. Each phase was sealed off from the rest of the ED and kept under negative pressure to ensure patient safety throughout the project. System upgrades included medical gas, electrical, mechanical, plumbing, nurse call, and communications. All systems were kept online during construction, with outages closely coordinated and largely completed during off hours. Since the work involved loud noise and vibration (e.g., concrete cutting, demo, etc.), work was carefully coordinated with ED Staff and the Operating Rooms on the floor directly above the construction, which are Neurology and Cardiac areas. Updated finishes included flooring, casework, ceilings, paint, and wall protection throughout. The project also included new X-Ray and CT areas, including all overhead support work for the X-Ray and CT machines, as well as lead lining of all the doors, windows, and walls in those rooms. New reception and security areas were installed, including bullet-resistant glass and walls. A portion of the ED containing behavioral health exam rooms received updated finishes and anti-ligature updates. Initially, the project was bid to be completed in 28 phases; however, with some outside-the-box thinking and close coordination with the ED Director, the number of phases was reduced to 8, expediting project completion.

1708 LACEY BUILDING RENOVATIONS

The 1708 Lacey Building Renovation was a complete remodel of an existing 3-story medical office building that was essentially a separate building from the main hospital. The building systems and structure, which were old and failing, were upgraded. All interior walls and finishes, mechanical, electrical, and fire sprinkler systems were removed and replaced. The entire building was tuckpointed, all the glass and window frames were replaced, and the roof was replaced. A new drive-up/drop-off lane was constructed along the main roadway to the hospital, along with new entryway canopies. The sewer system was reworked, and the existing parking lot, retaining wall system, and landscaping were completely replaced. This project was completed over 8 to 9 months. The new layout included offices, education areas, cardiac rehab, lab areas, and facilities management areas. Challenges on this project included keeping the hospital’s main server room active throughout the entire project while completing demolition and replacing all building systems, as well as planning for extra-long lead times (24-30 weeks) on the main building systems that were replaced. Additionally, extra safety measures and planning were necessary, as a large section of the tuckpointing and window replacement was completed off a swing scaffold, similar to what window washers use on skyrises.