Things are moving right along at the Saint Francis East Prairie Clinic project. The building is fully dried in and HVAC & electrical rough ins are complete, providing cooling and power. Additional milestones include completion of the EIFS installation and detailing on several sides of the building and placement of some exterior signage.
Crews are currently working on overhead electrical, underground electrical and communication, gas piping, EIFS detailing, parking lot curbs, gutters and sidewalk, drywall finishing , panting, wall tile and wall protection.
Coming up next: Paving, light poles, interior lighting, acoustical ceiling, window shades, casework, exhaust fans/diffusers, sprinkler heads and plumbing fixtures.
#RobinsonProjects #RIHCContracting #HealthcareConstruction